High Bay Counts, DTL Photocontrols, and a Fancy Chandelier: A Lighting Procurement FAQ From Someone Who Got It Wrong First
-
How many high bay lights do I need?
-
What does an LED driver actually do, and why does it matter?
-
Are DTL dark-to-light photocontrols worth the extra line item?
-
Why does Crawfordsville, Indiana keep coming up when I search Acuity Brands lighting?
-
Where does a fancy chandelier fit into a commercial lighting job?
-
Will a supplier actually care about a small order?
-
What's the process failure that cost me the most?
I've placed commercial lighting orders for about seven years now. Roughly $2.1M in spend — maybe $1.9M, I'd have to pull the report. Along the way I've made enough documented mistakes that I now own the checklist our team uses before anything gets signed.
These are the questions I get asked most often, answered with the mistakes attached. Skim the list, jump to what you need.
- How many high bay lights do I actually need?
- What does an LED driver do, and why is it on my quote?
- Are DTL dark-to-light photocontrols worth it?
- Why does Crawfordsville, Indiana keep coming up?
- Where does a fancy chandelier fit into a commercial job?
- Will anyone care about my small order?
- What's the process failure that cost me the most?
How many high bay lights do I need?
Don't start with square footage. Start with three things: racking height, aisle width, and whether the space under the fixtures is steel racking or open floor.
We did a 22,000 sq ft warehouse in 2021. The first calculation came back at 18 fixtures. We installed them, walked the floor, and half the light was dying in the top of the racking. Final count was 26 — and about half of those were narrow-distribution units aimed down the aisles instead of wide-distribution units washing the open floor. Same building, different answer.
Get photometric files from whoever you're buying from (any legitimate manufacturer publishes them). Then work from IES recommended practice documents rather than a forum post that says "X lumens per square foot." And do not size to a maintenance factor of 1.0. Three years of dust on a lens in a manufacturing plant doesn't give you catalog lumens. Sizing to a 1.0 factor is not optimism. It's a gap you'll be explaining to your facility manager.
What does an LED driver actually do, and why does it matter?
It converts the AC at the wall into the DC the LED chips need, and meters the current to whatever your dimmer asks for. Sounds like a $40 part. It is a $40 part until it isn't compatible.
September 2022, I placed a 60-fixture order. Fixtures were fine. The control panel was DALI. The drivers were 0-10V. We bought 60 fixtures and then spent $3,400 replacing drivers with the right protocol, plus three weeks of schedule. Nobody checked one line on a spec sheet. That's the whole story.
Now I have a rule: dimming protocol of the driver gets confirmed in writing before any PO is released. And photograph the driver label on the first unit that lands. Future-you trying to find a replacement driver eighteen months later will thank present-you.
Are DTL dark-to-light photocontrols worth the extra line item?
DTL means dark-to-light: on at dusk, off at dawn, no one thinking about it. If you're specifying DTL Acuity Brands photocontrols, that switching logic is exactly what you're paying for.
Worth it when: the circuit is exterior, the on/off window is predictable, and there's no network control doing the scheduling already. Parking lot entrances, loading areas, sign lighting, corners of a site. Not worth it when: the area runs 24/7, or the site already has a central control layer that handles timeclock schedules.
"Skip the DTL, the lot's got garage lighting under it anyway." — me, 2020.
Eighteen exterior fixtures ran about two hours too long every day for eleven months. (Should mention: that site had no timeclock either, so "skip it" really meant "leave it to whoever opens the gate.") It was my maintenance tech who finally flagged it, not me.
One more thing: per the FTC Green Guides (16 CFR Part 260), efficiency and environmental claims need substantiation. So when a cut sheet says "saves 60% energy," that's a claim to verify against your utility rate and burn hours — not a number to copy into a proposal.
Why does Crawfordsville, Indiana keep coming up when I search Acuity Brands lighting?
Crawfordsville, Indiana is one of the manufacturing sites behind Acuity Brands lighting, which is why the phrase "acuity brands lighting crawfordsville indiana" shows up in procurement searches. People typing it are usually trying to figure out where a given order ships from.
Here's my advice: don't infer. Ask. Origin affects lead time, freight, and — the part nobody thinks about — whether you can get four replacement units at reasonable speed when a fixture fails and it's the only thing between you and a failed inspection.
This was accurate as of January 2025. Plant origins and product assignments shift, so confirm the ship-from point on the quote before you commit.
Where does a fancy chandelier fit into a commercial lighting job?
Usually lobbies, hospitality, restaurants. Not warehouses. And they bring two problems nobody warns you about: the driver (yes, again — a driver, packed into a space you can't reach), and the controls.
We installed one in a 2021 lobby refresh. The driver sat in the canopy with no access panel. The first driver failed at about fourteen months. Dropping that fixture from the ceiling to open the canopy ran nearly $900, which is absurd for a component that costs a fraction of that.
If you're ordering one — even a single one — ask two questions. Can the driver be replaced without removing the whole fixture, and will they sell you one unit. If the answer to the second is a 25-piece minimum, fine, that's their model. Just find that out before your install date, not after.
Will a supplier actually care about a small order?
Real talk: you can tell early. The way a vendor handles a six-piece order tells you most of what you need to know about how they'll handle a six-figure one.
In 2018 I needed six replacement parts for a lobby retrofit. Two suppliers wouldn't even quote it. The third emailed back and said they batch small items into their weekly run — not fast, but on the calendar and priced sanely. I still buy from them. Last year that relationship was a $21k single order.
To be fair: small quantities never price like volume. That's freight and setup cost, not contempt. The thing I push back on is the silence, not the number.
What's the process failure that cost me the most?
We didn't have a formal delivery-confirmation process. I found out the expensive way — three separate orders changed carriers without notifying us, and one sat on our dock for two days unaccounted for because no one reconciled the packing slip against the delivered count.
The third time it happened, I built a nine-line pre-PO and receiving checklist. First four lines:
- Delivery date confirmed in writing, not verbally.
- Driver and dimming protocol confirmed.
- Ship-from location and freight terms confirmed.
- Delivered count reconciled against packing slip on arrival.
In the past eighteen months that checklist has caught 31 issues before we released payment. Thirty-one. Against one $7,200 error on a single order in 2022, it's the cheapest thing we own.
Nine lines. No software. Done.